Thursday, June 29, 2017

6-29-17 Arrival of members, wrapping up painting



7:00am Arrived on site

7:05am Arrivalnof first set of members










8:00am Began painting remaining members

9:00am Arrival of second set of members






10:00am Members placed on sawhorses for cutting and painting





12:30pm Arrival of third and final truck for the day



1:00pm Continued cutting members



Wednesday, June 28, 2017

6-28-17 Continued Handrail removal and 3rd Coat on covered truss

 

7:00am Arrival on site

7:00am Crew continued grinding out the existing welds on the east approach

 

8:30am Crew Continued making a flush surface for bearing plates and worked on creating a layout plan

9:00am 3rd paint coat being applied

 

 

 

 

Mm test (paint thickness) Test 1: 463
Test 2: 503
Test 3: 498
Test 4: 521
Test 5: 478

 

Tuesday, June 27, 2017

6-27-17 Handrail demo and grey painting of covered truss

 

7:00am Arrival on site

7:00am Crew began demolition of existing handrail and layout of new temporary handrail

7:45am Grey coat began

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

 

 

 

 

 

 

 

 

 

 

 

 

Monday, June 26, 2017

6-26-17 Sandblasting of remaining covered truss

 

7:00am Arrival on site

2:00pm Finished Sandblasting of covered truss and began painting zinc onto the remaining covered memebers

 

 

 

 

 

 

4:00am Apache finished painting the zinc on the covered truss