Wednesday, June 28, 2017

6-28-17 Continued Handrail removal and 3rd Coat on covered truss

 

7:00am Arrival on site

7:00am Crew continued grinding out the existing welds on the east approach

 

8:30am Crew Continued making a flush surface for bearing plates and worked on creating a layout plan

9:00am 3rd paint coat being applied

 

 

 

 

Mm test (paint thickness) Test 1: 463
Test 2: 503
Test 3: 498
Test 4: 521
Test 5: 478

 