7:00am Arrival on site
7:00am Crew continued grinding out the existing welds on the east approach
8:30am Crew Continued making a flush surface for bearing plates and worked on creating a layout plan
9:00am 3rd paint coat being applied
Mm test (paint thickness) Test 1: 463
Test 2: 503
Test 3: 498
Test 4: 521
Test 5: 478