Thursday, September 14, 2017

9-14-17 Running board repair


7:20am- Continue to set new running boards at the West approach.

8:52am- Cleaning the West abutment where the main truss is bolted down.

9:52am- Welding the final vertical supports for the new handrail.

10:24am- Continue to touch the paint up at the East approach.

11:31am- Securing running boards down at the East approach.

1:24pm- Continue to touch up paint at the East approach main truss.

2:15pm- Setting lumber curb at the East approach heading West.

3:00pm- Removing more scaffolding under the Weast approach of the bridge.

3:47pm- Continue to set and secure running boards on the main truss heading West.

4:22pm- Continue to remove Scaffolding from under the West approach of the bridge.

5:00pm- Results from the day.