Friday, September 15, 2017

9-15-17 securing Lumber Curb


8:11am- Continue to secure running boards and curb lumber




9:24am- Continue to disassemble scaffolding under bridge.

10:45am- Continue to touch up paint on the North West side of the bridge.



12:48pm- Setting and securing Curb lumber at the West approach..

2 comments:

  1. No new updates? Today is 9/20 bikes blues & bbq is about to be in full swing, with this area being a high interest point I would have expected an update.

    ReplyDelete
    Replies
    1. Thank you for your comment. The County, State, Contractor, and Engineer met onsite yesterday to do a walk-through inspection. The contractor has a few little items to finish up but the bridge should be open for bike traffic. We thank you for your patience.

      Delete