Tuesday, September 5, 2017

9-5-17 Fabricate Bridge Shoring


8:10am- Continue to cut wood inserts for the new handrail.

9:14am- Removing excess vertical support for the new handrail.

11:07am- Setting first part of the Beidge Shoring on the main truss for the verticle pin repair.







12:40pm- Continue to fabricate more of the Bridge Shoring for the vertices pin repair.



1:34pm- Setting the second support for the verticle pin repair at the West approach.


 
2:25pm- Continue to hang brackets for the Verticle pin repair at the West approach

3:30pm- Painting the underside of the bridge at the West approach.


435:pm- Continue to set up Bridge Shoring at the West approach.