8:40am- Fastening coil rods for the Bridge Shoring to install new I bars.
9:59am- Removing part of the main truss to install a portion of the new I bar
11:14am- Continue to install new wood on built handrail.
11:25am- Removed first piece of main truss in order to install new I bar.
2:15pm- Removing another section of the main truss, at the West approach for the new I bar installation.
3:00pm- Results from primer underneath bridge at the West approach.
3:51pm- Continue to install wood inserts into the new handrail heading towards the West approach.