8:47am- Buinding forms and rebar baskets around floor stringers for concrete pour tomorrow. 
10:09am- Continue to build forms and rebar baskets.
10:47am- Continue to build scaffolding.
3:33pm- Finished building rebar baskets for bent caps 5-6.
4:15pm- Continue to blast North end of bridge.
5:19pm- Finished removing deck beams from bent 3-4