7:00am Arrival on site
8:00am Finished bolting down C clamps
11:00am Painting of second coat on members
12:30pm Installion of running boards
1:00pm Pour Concrete @ west abutment
Slump: 4in
2:00pm Arrival of another forklift and compressor
3:00pm Final coat of paint added to memebers
4:00pm Decking being placed after Concrete pour