Thursday, July 13, 2017

7-13-17 Continued Scaffolding, Floor Beam strengthening, painting, Handrail installation



7:00am Arrival on site



8:00am Finished bolting down C clamps 









11:00am Painting of second coat on members



12:30pm Installion of running boards



1:00pm Pour Concrete @ west abutment 
Slump: 4in







2:00pm Arrival of another forklift and compressor



3:00pm Final coat of paint added to memebers







4:00pm Decking being placed after Concrete pour






No comments: