7:00am Arrival on site
7:00 Continued Floor Beam strengthening
7:00am Rebolting of decking due to weight of the forklift causing the boards to pop out of place
7:30am Scaffolding crew continued work on East side of the truss
Handrail installed yesterday
8:30am Began placing members on sawhorses for painting
11:00am Second coat on members waiting for third coat
11:00am Scaffolding Continued
3:30pm Began forming at west abutment