Tuesday, July 11, 2017

7-11-17 Floor Beam Strengthening, scaffolding, painting of members



7:00am Arrival on site

7:00 Continued Floor Beam strengthening



7:00am Rebolting of decking due to weight of the forklift causing the boards to pop out of place

7:30am Scaffolding crew continued work on East side of the truss

Handrail installed yesterday 





 8:30am Began placing members on sawhorses for painting





11:00am Second coat on members waiting for third coat






 11:00am Scaffolding Continued




 
3:30pm Began forming at west abutment