7:00am Arrival on site
7:00am Began Placement of beams
8:30am Began welding beams to plates
9:00am Arrival of more paint
12:00pm Continued welding beams
2:00pm Finished welding and began deck placement
2:00pm More members painted with second coating
Scaffolding only got 1 crosswalk setup