8:01am- Removing both I beams on the outside of the East approach
8:05am- Continue to erect scaffolding on the East approach
11:01am- Continue to coat beams with Zinc primor.
11:24am- Holes drilled and rebar set at bent 6
11:52am- Continue to assemble scaffolding on the Southeast end of bridge
1:23pm- Continue to remove I beams from East approach in between bents 4-5
1:46pm- Cutting new approach beams to fit
4:51pm- Finished frame structure for bent 6 on East approach. Ready for concrete pour Monday morning.