Thursday, July 20, 2017

7-20-17 Disassembling East approach


8:01am- Removing both I beams on the outside of the East approach

8:05am- Continue to erect scaffolding on the East approach

11:01am- Continue to coat beams with Zinc primor.


11:24am- Holes drilled and rebar set at bent 6


11:52am- Continue to assemble scaffolding on the Southeast end of bridge
1:23pm- Continue to remove I beams from East approach in between bents 4-5

1:46pm- Cutting new approach beams to fit



4:51pm- Finished frame structure for bent 6 on East approach. Ready for concrete pour Monday morning.