Friday, July 14, 2017

7-14-17 Handrail Installation, Scaffolding work, Screen Placement



7:00am Arrival on site

7:00am Welding final post on west approach



7:30am Installation of final Handrail channel on the west approach

8:00am Continued installing screens







9:00am Arrival of materials for decking underneath bridge





1:00pm Running boards fully installed



1:30pm Installation of timber in Handrail inserts



2:30pm Began demolition of bent 2







4:00pm Installation of steel plates at west approach