7:00am Arrival on site
7:00am Scaffolders continued development of lower decking
7:00am Began lower chord strengthening/Continued deck placement at West approach
9:00am Moved tarp to west side of truss
10:00am Painted more members
Continued redecking and floor beam stregthening
3:30pm Arrival of more scaffolding