Wednesday, July 12, 2017

7-12-17 Floor Beam strengthening, scaffolding, forming up west diaphragm



7:00am Arrival on site

7:00am Scaffolding crew, Floor Beam drilling and bolting crew, and forming crew all began work











10:00am Began painting more members





10:30am Finished welding Handrail on South side of the bridge at the west approach



12:00pm Continued Handrail installation









4:00pm Began placing screen