Wednesday, July 26, 2017

7-26-17 East approach floor stringers Bent 5-6


7:14am- Finish blasting top half on North side of bridge, should be painting later this afternoon.

7:28am- Results from painting floor stringers yesterday.



8:43am- Setting painted floor stringers in between bents 5-6. 





1:46pm- Placing timber deck back on the East approach.


4:01pm- Continue to place timber decking from Bent 5-6.

4:08pm- Applying primer to the North side of the bridge.