7:11am- Continue to remove concrete from around floor stringers at bent 5 on the East approach
8:00am- Painting crew are still applying plastic sheeting over bridge for protection and containment of material when blasting.
9:49am- Crew removing existing concrete from bent 6
10:09- Continue to put first coat on beams
12:20pm- Continue to remove concrete from around I beams at bent 6
1:07pm- Cut and removed I beams from bent 5 to bent 6
1:18pm- Crew removing existing concrete from around I beams located at bent 4 at the East approach
4:07pm- Painting and blasting crew still applying plastic sheeting to protect area during construction
4:41pm- I beams removed from bents 4-6