8:52am- Removing last I beam on the East approach from Bents 4-5
9:27am- Applying epoxy coating to floor stringer beams.
11:16am- Removing existing concrete from bent 4
11:27am- Paint thickness readings from first coat of epoxy on floor stringer beams
12:55pm- Continue to erect scaffolding on the East end of the bridge in order for construction crew to proceed to the west after removing floor decking.
3:06pm- Drilling bent 4 for rebar.