Tuesday, August 1, 2017

8-1-17 Removing beams from bent 3-4


8:09am- Removing I beams in between bent 3-4.

8:30am- Paint crew left for the day due to wet conditions.
9:21am- Continue to remove I beams in between bent 3-4

12:16pm- Removing existing concrete From bent 4. Forming and epoxying rebar for tomorrow's pour.





3:05pm- Saw cutting old bearing plates out and drilling new holes to epoxy new pads in place.