Monday, August 28, 2017

8-28-17 Deck removal for I beam placement


7:58am- Redults from Friday's painting at the East approach main truss.



8:24am- Continue to weld handrail on main truss area heading Northwest.

10:04am- Removing running planks to expose Deck timber.

12:38pm- Removing Deck timber to expose old I beams. 

2:14pm- Installing new I beams on the main truss heading Notthwest



3:40pm- Welding I beams to horizontal floor beams

4:52pm- Set wooden decking back into place.