Thursday, August 10, 2017

8-10-17 Continue J plate repair


7:43am- Welding handrail on East approach.

10:16am- Continue with J plate repair on lower verticle pins @ East approach.



10:40am- Continue to remove rivets for the J plate repair.
1:28pm- Installing C channel on the 2nd verticle East approach, Southwest side of the bridge.

2:42pm- Results from this morning, primer on I beams and handrail.



3:05pm- Continue to bolt wooden deck down to the new C channel and I beams.

4:21pm- Removing rivets and old channel from bottom of verticles 



4:28pm- Building more scaffolding for the underneath of the bridge.

4:37pm- Painted beams and handrail.