7:43am- Welding handrail on East approach.
10:16am- Continue with J plate repair on lower verticle pins @ East approach.
10:40am- Continue to remove rivets for the J plate repair.
1:28pm- Installing C channel on the 2nd verticle East approach, Southwest side of the bridge.
2:42pm- Results from this morning, primer on I beams and handrail.
3:05pm- Continue to bolt wooden deck down to the new C channel and I beams.
4:21pm- Removing rivets and old channel from bottom of verticles
4:28pm- Building more scaffolding for the underneath of the bridge.
4:37pm- Painted beams and handrail.