7:34am- Continue to weld handrail on the main truss heading Northwest.
8:41am- Results from painting underneath the bridge yesterday.
10:11am- Removing Deck wood to expose I beams and C channel.
12:08pm- Wooden decking is removed and old I beams are exposed.
12:51pm- Removing I beams from main truss at Northwest end.
1:43pm- Continue to set I beams at the Northwest end of the bridge
2:40pm- Painting the underside of bridge, heading towards the West approach.
3:40pm- Finished setting I beams and C channel. Ready for wooden decking.