Wednesday, August 30, 2017

8-30-17 Deck removal for I beam placement


7:34am- Continue to weld handrail on the main truss heading Northwest.

8:41am- Results from painting underneath the bridge yesterday.



10:11am- Removing Deck wood to expose I beams and C channel.



12:08pm- Wooden decking is removed and old I beams are exposed.



12:51pm- Removing I beams from main truss at Northwest end.

1:43pm- Continue to set I beams at the Northwest end of the bridge

2:40pm- Painting the underside of bridge, heading towards the West approach.

3:40pm- Finished setting I beams and C channel. Ready for wooden decking.