Tuesday, August 22, 2017

8-22-17 Deck removal for I beam placement


8:25am- Drilling new holes in existing wooden floor decking to set clamps.

8:26am- Cutting wood for handrail channel at the East approach.

8:52am- Welding handrail to new uprights

RAIN DELAY

10:51am- Continue to weld uprights for handrail installation.
12:05pm- Continue to cut wood for handrails
2:37pm- Removing more wooden decking to replace old I beams


2:49pm- Remove I beams from main truss, heading West.

4:02pm- Continue to remove I beams from main truss.