7:34am- Drilling new holes in old wooden decking to attach to new I beams
9:00am- Grinding old paint prepping for primer.
9:51am- Welding new handrail to verticle supports.
11:12am- Continue to cut treated wood for handrail inserts.
12:23pm- Remove wooden decking to expose old I beams and C channel to be replaced.
1:59pm- Removing old floor I beams and prepping for installation of new beams and C channel
3:44pm-Continue to set I beams and C channel into place.