7:52am- Setting floor stringers between bent 3-4 on the East approach.
8:47am- Continue to blast on the North end (West approach) of the bridge.
11:24am- Floor stringers set and placing wooden deck back in place.
3:16pm- Continue to set wooden deck in between bent 3-4. Built rebar baskets for bent 4 diaphragm.
4:15pm- Continue to build handrail on the East approach