Thursday, August 3, 2017

8-3-17 Setting beams bent 3-4


7:52am- Setting floor stringers between bent 3-4 on the East approach.

8:47am- Continue to blast on the North end (West approach) of the bridge.

11:24am- Floor stringers set and placing wooden deck back in place.

3:16pm- Continue to set wooden deck in between bent 3-4. Built rebar baskets for bent 4 diaphragm.

4:15pm- Continue to build handrail on the East approach