8:40am- Removed running planks to access wooden deck boards for removal.
12:17pm- Wooden deck boards and I beams removed.
12:39pm- Results from painting East approach handrail on Friday.
12:45pm- Continue to set new I beams in place.
2:17pm- Welding new I beams in place to existing floor beams.
4:15pm- Setting C channel on outside edges.