Wednesday, August 2, 2017

8-2-17 Concrete cap pour


7:59am- Continue to blast on the Northeast side of the bridge

10:15am- Pouring concrete caps at bent 5-6.





10:40am- pour concrete bearing pads at bent 4 and set bearing plates

1:16pm- Finished bent 6, waiting for wood decking installation.
1:36pm- Installing handrail on the Southwest side of the East approach.

2:30pm- Continue to install handrail on the East approach

3:11pm- Primer the North end of the bridge.

3:27pm- Fabricating uprights to install handrail on Southeast side of the East approach.