Monday, August 21, 2017

8-18-17 Deck removal for I beam placement

 
7:45am- Removing I beams from main truss deck at the East approach 

8:53am- Installing new I beams at the first main truss on East approach.



9:44am- Continue to install I beams at the first main truss on the East approach.

10:45am- Results from morning primer on East approach handrail.





11:08am- Continue to place I beams at the first main truss on the East approach.