7:40am- Cutting welds from old I beams and bearing pads
9:13am- All beams removed from the first truss span heading west.
12:20pm- Installing new I-beams on the first truss span.
1:30pm- Removing C channel and handrail on the first truss span heading West.
1:55pm- Continue to primer the North end of bridge.
3:51pm- Setting wooden deck back on main truss on the East end heading West.