Monday, August 7, 2017

8-7-17 Removing I beams from main truss


7:40am- Cutting welds from old I beams and bearing pads

9:13am- All beams removed from the first truss span heading west.

12:20pm- Installing new I-beams on the first truss span.

1:30pm- Removing C channel and handrail on the first truss span heading West.



1:55pm- Continue to primer the North end of bridge.

3:51pm- Setting wooden deck back on main truss on the East end heading West.